Seaside’s Fred Loser remembers when things were so quiet at Providence Seaside Hospital that they would send doctors home for lack of business.

“When I came here in 1990 and ’91, there were days when there was nobody here. With a full staff, they’d send people home to save expenses. Now look at it — you can’t even get in the door.”

In the last 30 years — since the hospital’s last emergency room remodel — those numbers have exploded.

Today, emergency room manager Cherie Echelbarger said the emergency room sees about 10,000 patients a year, or about 25 or 30 a day, much more on holidays and seasonally.

Don Lemmon, chief executive of Providence Seaside, and Kimberly Ward, executive director of the Providence Hospital foundation, welcomed supporters, staff and community members to a “peek behind the curtain” of project renderings.

“Transforming our emergency services is going to be really monumental here at Providence and the care we are able to provide the people who use our services here,” Lemmon said.

As he spoke, the pounding of hammers and buzz of power tools could be heard from work underway in the project’s phase one.

The project began in August 2017 when the foundation and community partners determined there was support and capacity to move forward.

In December 2017, the foundation board launched the beyond 911 to expand emergency care at Providence Seaside Hospital, to raise $1.5 million toward a $5 million rebuild. The campaign was successful by December 2018 and announced at the Festival of Trees gala.

On Thursday, Josh Kolberg of PKA Architects described the process of drawing and redrawing plans before construction.

The new waiting area will have “nice big windows,” new furniture and specialty ceilings, Kolberg said.

The reception area will serve as an after-hours entrance, with a security room, nine treatment rooms and triage space, including an airborne infection isolation room.

Two rooms are designed as “enhanced patient safety rooms” for patients described as difficult or needing special care.

Two of the rooms will be double occupancy.

The department is now in phase one of construction, building out the triage room, reception area, security office, waiting space and a portion of the nurse’s station.

When phase one is complete in November, the primary activities of the emergency department will move into that space, and they’ll starting building out phase two, Kolberg said. Phase three includes completion of a treatment room.

Completion of all three phases is expected mid-June 2020.

Duane Mullins, general manager of Medix Ambulance, said the added rooms will provide needed treatment areas. “The access doesn’t change,” Mullins said. “We back into the same door. People get seen when it’s really busy — and it’s more ‘really busy’ than it used to be.”

Recommended for you

(0) comments

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.